Please see the update to the pulverizing and paving schedule:
- Pulverizing, shaping, and grading to a gravel condition occurs July 6th – 7th
- Inspecting gravel conditions occur July 8th-9th
- Pouring concrete driveway aprons occur July 8th – 9th. Drying and curing of concrete will take 7 days and will require use of parking outside of the area of construction. Street parking will be temporarily allowed on Standish Ln and N. Elmwood during this time period.
- Repaving of streets should be completed by the 2nd week in July
Residents should be advised that all of these dates are subject to change.